Matiari-Lahore HVDC Transmission Project | PIP

Matiari-Lahore HVDC Transmission Project, The Matiari-Lahore high-voltage direct-current (HVDC) Transmission Line Project is a 660 Kilovolt line that is near completion. The project comes under the Early Harvest projects of the China-Pakistan Economic Corridor. It is aligned with the coal-fired power projects in Sindh and transfers 4000MW electricity from Port Qasim and Thar to central Pakistan.

This project is important for the evacuation of electricity from these regions and the general improvement of the grid structure of Pakistan. The Matiari-Lahore Transmission Line Project is financed through both the private sector and foreign investment. It is the first project of its kind in the country. The transmission line will cover up to 878km.

Matiari-Lahore HVDC Transmission Project-pip

A feasibility study for Matiari-Lahore HVDC Transmission Line Project was conducted in 2013, through SNC Lavalin which is a Canadian company that provides procurement, engineering, and construction services. SNC Lavalin evaluated different options for the expansion of the Pakistani Transmission Line System. Based on the information procured from this study, the National Transmission & Despatch Company (NTDC) suggested the construction of HVDC Transmission Lines to transmit large amounts of power from the Southern part of Pakistan to the Central part.

This project goes back to the Cooperation Agreement signed in 2015 when President Xi Jinping visited Pakistan. The Ministry of Water and Power of Pakistan and State Grid Corporation of China entered into several agreements for the project at the 6th Meeting of the Joint Cooperation Committee on CPEC in December 2017. And a Power Transmission Service and Implementation Agreement was signed in May 2018.

After 27 months of construction, the project is nearing completion in 2021. The total cost of the project is 2,000 Million USD. 

Tariff

HVDC Transmission-pip

The Levelized tariff in the matter of Matiari-Lahore 4,000 MW E 660 KV HVDC Transmission Project was decided to be at RS/- 0.7435 per KW/h according to the decision of the authority in the matter of Petition filed under Rule 3 of the NEPRA Rule, 1998 for Modification of the Tarif Decision on May 04, 2017.

Financing

HVDC Project-pip

The Debt-Equity Ratio for the project is at 80:20 with the interest rate lying at 5.64%, loan tenure of 10 years repayment period, and 27 months grace period. The annual debt servicing is Rs/- 0.5227 per KW/h over 20 years. The transmission line is financed through the private sector and it is being built under Build Own Operate & Transfer.

Operator

China Electric Power Equipment and Technology Co. Ltd. (CET) is the implementer and operation platform of State Grid Corporation of China (SGCC) for carrying out Engineering-Procurement-Construction (EPC) business internationally. CET is a subsidiary of SGCC which will operate the Matiari-Lahore Transmission Line for 25 years and then it will be transferred to the National Transmission and Dispatch Company which is a Pakistani government-owned power transmission company.

CET may also provide more transmission lines to Pakistan, for example, the Port Qasim-Faisalabad transmission line.

Route Details

The transmission line is stretched from Matiari in the province of Sindh to the Nankana Sahib district near Lahore, Pakistan.

In Sindh, the HVDC transmission line goes through the districts of Matiari, Sanghar, Khairpur, Sukkur, and Ghotki for a total distance of about 315km.

The line enters the province of Punjab from Rahim Yar Khan then passes through Bahawalpur, Bahawal Nagar, Pak Pattan, Okara, Kasur, and ends at Nankana Sahib for a distance of about 551km.

Most of the line route (more than 60%) lies in desert areas in order to avoid various issues such as settlement and conflicts related to the securing of right-of-way.

best HVDC Transmission Project in Lahore-pip

Transmission Line Design

It is a bi-pole HVDC line with two converter stations at both ends. It has three repeater stations and two grounding electrode stations.

A total of 1898 self-supporting steel lattice towers are installed; 681 of these towers are located in Sindh while the rest is in Punjab.

The converter stations are connected with various power stations that are developed under the CPEC. The Lahore Converter station is connected to the new substation from where the electricity is transferred to the national grid.

Both the converter stations have a valve hall containing a control building, thyristor valves, and an outdoor switchyard that houses the harmonic filters and power transformers.

Power Supply

The Matiari converter station receives power supply from a 185km long 500kV AC transmission line coming from the Port Qasim power plant and a 200km long 500kV AC transmission line from the Hubco power plant.

The SSRL Thar Block 1 power plant and Engro Thar coal power plant are also connected to the Matiari converter station through a 275km and a 250km AC transmission line respectively.

Additional Information

The Matiari-Lahore Transmission Line is mainly designed to transmit electricity generated from coal power projects such as Port Qasim Power Project and Engro Thar Coal Power Project. The government of Pakistan has allotted two pieces of land for building and installing converter stations; one for converting alternate current to direct current in Matiari and the second near Lahore for converting DC to AC.

Leave a Comment